ELN-001Active · approved 20 Mar 2026Operational

Raw material and packaging supply disruption causing production stoppage

25
Inherent
Critical
I5 × L5
10
Residual (current)
Medium
I5 × L2
5
Target (appetite)
Low
I5 × L1 · by 31 Mar 2027
Residual score by quarter
Q1
Q2
Q3
Q4

Shortfalls in maize, wheat or packaging materials stop the CST mill lines.

Root causes

  • Inadequate maize and wheat cover
  • Delayed sourcing and long supplier lead times
  • Port and transport delays

Consequences

  • Production stoppage
  • Lost sales and market share
Owning unit
Unga Limited › CST › RMPM
Also affects
None
Linked group risk
None