Road network damage delays distribution to depots

16
Inherent
Critical
I4 × L4
8
Residual (current)
Medium
I4 × L2
8
Target (appetite)
Medium
I4 × L2 · by 31 Mar 2027
Residual score by quarter
Q3
Q4

Washed-out roads during the rains delay deliveries from CST to regional depots.

Root causes

  • Washed-out feeder roads
  • Single transport route to western depots

Consequences

  • Late deliveries and stock-outs at depots
  • Higher transport costs